Miami-Dade's proposed Seaquarium lease runs 99 years with at least $1.1 million a year in rent. A county committee deferred it Nov. 10 to its next meeting.

The closed Miami Seaquarium on Virginia Key would be rebuilt by a Terra-affiliated company under a 99-year lease that Miami-Dade County commissioners now have in front of them. The tenant would pay the county at least $1.1 million a year once the first phase opens.

The lease is file 261973, a late addition to the agenda of the county’s Recreation, Tourism and Resiliency Committee on Tuesday, Nov. 10. Commissioner Raquel Regalado, whose District 7 includes Virginia Key, is the sponsor. The full package runs to 249 pages, including the lease itself.

Updated Nov. 13: The committee deferred the lease on Nov. 10 to its next meeting, according to the county’s legislative record. No vote was taken. The record does not yet list the date of that meeting.

The deferral means the lease cannot reach the full County Commission until the committee takes it up again. The separate right-of-way item, file 261821, was still listed as in committee on Nov. 13.

What the lease would build

The tenant is Resilient Aquarium LLC. The mayor’s memo says the company is wholly owned by David Martin, the co-founder and chief executive of Miami developer Terra. Under the county’s lease package, the tenant would build:

  • a new accredited aquarium with no marine mammals
  • marine and aquatic experiences focused on Biscayne Bay
  • an education, conservation and research center
  • wellness spaces tied to the waterfront
  • a “fisherman’s village” with marine-oriented stores and places to eat and drink
  • a public marina with wet slips, a dry stack and a fuel dock
  • a restored Buckminster Fuller dome, reused as event space
  • a restored Flipper House

The tenant must spend at least $100 million on the project. It must also spend at least $10 million on public features that are free to use. Those include a Baywalk along the whole waterfront, green space beside it and a kayak and canoe launch. The tenant would run and maintain them for the life of the lease.

The money

Bar chart of guaranteed yearly rent for the Miami Seaquarium site: $750,000 under the current lease, $1,000,000 under the current lease when revenue tops $7.5 million, and $1,100,000 under the proposed lease, which rises with inflation by up to 3% a year.
Guaranteed rent under the current and proposed leases. Chart by Miami Local Today
Share this chartFacebookWhatsAppX

The yearly rent is the larger of two figures, according to the mayor’s memo:

Rent type Current lease Proposed lease
Guaranteed rent $750,000, or $1 million if revenue tops $7.5 million $1.1 million, rising with inflation by 0% to 3% a year
Share of revenue, attractions and stores Not given in the memo 3% of gross revenue
Share of revenue, marina Not given in the memo 5% of gross revenue

Before the site opens, the tenant would pay $250,000 a year in construction rent from site plan approval. No rent is due between the lease taking effect and site plan approval. The tenant would also pay the county a $100,000 project management fee in four parts.

Every dollar of rent goes into a county parks trust fund for long-term capital projects and deferred maintenance. The memo says the money can be spent anywhere in the county park system, not only on Virginia Key.

The tenant’s economic consultant, BusinessFlare, projects county lease revenue of about $1.45 million in the first year of operation. It projects about $2.51 million in year 15 and about $29 million over the first 15 years. Those are the developer’s projections, not county figures.

The waivers commissioners are asked to grant

Because Virginia Key is waterfront county park land, the lease needs a two-thirds vote of the full County Commission. The resolution also asks commissioners to waive three county rules:

  • the usual procedures for leasing county land
  • the requirement for two independent appraisals on county property worth more than $5 million
  • the rule requiring four weeks’ public notice before a no-bid lease of county property

The memo argues the bankruptcy court’s sale process already tested the market. It says that process reached more than 20,000 contacts and that 95 parties reviewed the Seaquarium materials. It also says the deal terms were made public when commissioners approved a term sheet on Dec. 2, 2025.

The memo gives one more reason for speed. The bankruptcy court approved the assignment of the current lease to the new tenant on Oct. 17, 2025, but the sale cannot close until the county approves this lease, “with the bankruptcy estate’s creditors awaiting distribution.” The parties expect to close 30 days after approval.

If the marina is not permitted

The marina still needs permits to use the bay bottom. The lease says that if the tenant cannot get them, it hands the submerged land back to the county. The $100 million minimum investment drops to match. If the county later leases that water to anyone else for a marina, the tenant gets first option on the same terms.

How the county got here

The county has leased the site for an attraction since March 9, 1954, and the Seaquarium opened the following year. The memo says the county sued in June 2024 to evict the last operator, MS Leisure Company, over breaches of the lease, including animal care and upkeep. MS Leisure filed for Chapter 11 bankruptcy in March 2025. The new lease would let the county settle or drop the eviction case once the sale closes.

A separate item, file 261821, would give the project a strip of county right-of-way about 1,474 feet long along the south side of the Rickenbacker Causeway. The strip is mostly Seaquarium parking lot and includes no travel lanes, sidewalk or bike path, according to the mayor’s memo on the right-of-way. That item goes to the county’s Infrastructure, Innovation and Technology Committee and needs a public hearing before the full commission.

This is not the marina deal Miami voters turned down on Nov. 3. That referendum covered a 45-year lease of the two City of Miami marinas on Virginia Key. Read the referendum results.

What it means for you

  • Nothing changes on Virginia Key yet. The Seaquarium stays closed. The lease was deferred in committee on Nov. 10 and still needs a two-thirds vote of the full County Commission.
  • The new attraction would have no dolphins or whales. The lease requires an aquarium without marine mammals.
  • You can follow the vote. The item’s status, votes and documents update on the county’s page for file 261973.
  • You can comment. Public comment is taken at County Commission meetings. Contact District 7 Commissioner Raquel Regalado’s office or speak at the meeting where the lease is heard.

We will update this story when the committee takes the lease up again.